Prairie Valley Road and Rosedale Avenue Progress Report

SCHEDULE IS SUBJECT TO CHANGE

During the weeks of August 16th to August 30th
Rosedale Avenue North
Our contractor is currently waiting for delivery of street lights as well as trees and shrubs to be installed in the medians and boulevards. Street lights are expected to be delivered early next month.

Street signage is to be installed in the following weeks and the landscape contractor will complete paver stone installation in the medians and boulevard areas.

Rosedale Avenue South
Sidewalk placement has begun and will continue until the middle of next week. Placement of road gravels and road graded in preparation for paving will take place shortly and paving is expected to commence during the week of the August 23rd.

Our electrical contractor will continue to convert overhead electric lines to underground by removing overhead cable and poles, and pulling cable through the newly installed ducts and junction boxes.

Prairie Valley Road
Removal of asphalt will commence in the week of August 16th as well as the removal of existing sidewalk to allow for new works in the Prairie Valley/Rosedale round about. Concurrently, road works including sub grade preparation and base placement, from Atkinson Rd. to Giants Head Rd. will be underway. In this phase of road reclaiming the contractor will leave the Atkinson Rd. and PVR intersection intact, utilizing Giants Head Rd. and Atkinson Rd. as a daytime detour while road building work proceeds on Prairie Valley Road.

Excavation in the intersection of Prairie Valley Road and Rosedale Avenue is expected to commence in the week of the 23rd for water separation including water line removal and installation, installation of a large concrete vault and installation of water valves and other related fittings.

There will be a Water Shut Off in effect on Thursday, August 19th at 7:00 pm until Friday, August 20th, at 7:00 am will take place in the areas of Giant's Head, Hespeler, Front Bench, Happy Valley and Gartrell Roads and all intersecting roads to allow for the installation of water works on Prairie Valley Road. H&M's intention is to proceed with water works surrounding the 'Water Vault' at Prairie Valley/Rosedale on Monday, August 23rd. This will mean water pressure reductions in the same area as above will take place on Tuesday, August 24th for 1 to 2 days. A Water Shut Off notice will be distributed prior to this activity.

Prairie Valley Road and Rosedale Avenue Progress Report -Your Summerland Chamber Road Construction Update Aug 18th - Summerland, Okanagan, BC

 

 

 

Raymond MAASKE,BBA, CCC, ACRE, ATM-B
Summerland & Penticton, Okanagan, BC

Website: http://www.HomeStarRealty.ca
E-mail:raymond@HomeStarRealty.ca
Phone:
250.488.8764

   Face book Raymond Maaske Home Star Realty icon Raymond MAASKE Home Star Realty Summerland & Penticton Okanagan BC Real Estate Raymond MAASKE Home Star Realty Summerland & Penticton Okanagan BC Real Estate Raymond MAASKE Home Star Realty Summerland & Penticton Okanagan BC Real Estate Raymond MAASKE Home Star Realty Summerland & Penticton Okanagan BC Real Estate Raymond MAASKE Home Star Realty Summerland & Penticton Okanagan BC Real Estate

"Oh by the way... I'm never too busy for your referrals"

 

0 commentsRaymond MAASKE • August 18 2010 04:51PM

Comments

This blog does not allow anonymous comments